Macao ready for launch of Hong Kong-Zhuhai-Macao Bridge

A press briefing on Macao's preparations for the launch of the Hong Kong-Zhuhai-Macao Bridge.

Macao is well prepared for the launch of the Hong Kong-Zhuhai-Macao Bridge, and has made ready its checkpoint services and public transportation facilities serving inbound and outbound movement via the Macao boundary crossing area of the Bridge.

The Government held a press briefing on Friday (19 October) to report progress on Macao’s preparations prior to the commissioning of the Bridge on Wednesday (24 October).

Several officials spoke at the press briefing. They were: the Government Spokesperson, Mr Chan Chi Ping; the Director of the Transport Bureau, Mr Lam Hin San; the Acting Director of the Infrastructure Development Office, Mr Lam Wai Hou; and the Deputy Commissioner of the Public Security Police Force, Ms Lao Wan Seong.

The facilities offering boundary crossing services for passengers and vehicles travelling between Macao and Hong Kong will be open 24 hours a day, once the Bridge is launched.

For the Zhuhai-Macao crossing, the facilities offering clearance service for vehicles will also be open round-the-clock. However, in order to ensure appropriate allocation of resources in the early stages of the Bridge’s operations, the facilities offering Zhuhai-Macao boundary crossing services for passengers will be closed between 10pm and 8am the following day. During that time, Macao travellers bound for Zhuhai (and vice-versa) can use instead the Zhuhai-Macao boundary point vehicle clearance channels or the Hong Kong-Macao boundary crossing point.

Customs clearance between Macao and Zhuhai will be carried out on a “Joint Inspection and One-time Release” principle, in order to make the process efficient for travellers using the Hong Kong-Zhuhai-Macao Bridge.

Under the new inspection system, travellers will be required to pass border controls only once – via either the automatic, semi-automatic, or manned channels depending on the identification documents – to complete the departure and arrival formalities.

Link roads between Rotunda da Amizade, the reclamation area Zone A on Macao peninsula and the Macao boundary crossing area will be open in order to serve traffic using the Bridge.

There will be two types of public transportation available for travellers using the Bridge. They are: regular bus services; and checkpoint shuttle services.

Checkpoint shuttles will be available to move people between boundary checkpoints.

There are two public car parks at the Macao boundary crossing area, which are located respectively at the east and west end of the artificial island serving that checkpoint. They are known as respectively the east car park and the west car park.

The east car park has a capacity for 3,000 private vehicles and the west one has room for a total of 3,089 private vehicles and 2,054 motorcycles.

Construction of the Macao boundary crossing area facilities commenced in December 2016 and fundamentals of the project were completed in December 2017.

The Macao boundary crossing area covers 71.6 hectares and has structures with a total gross floor area of 600,000 square metres. Facilities at the Macao boundary crossing area comprise: 53 buildings – about 40,000 square metres of gross floor area – for municipal use; and about 200,000 square metres of space dedicated to infrastructure including a road network, tunnels, flyovers, railway platforms and other municipal facilities.

View gallery


All information on this site is based on the official language of the Macao Special Administrative Region. The English version is the translation from the Chinese originals and is provided for reference only. If you find that some of the contents do not have an English version, please refer to the Traditional Chinese or Portuguese versions.