How to process
Required Document:
1. Application form (Format 009/DLA/DHAL, the form can be obtained from IAM);
2. Blueprint of the renovation project, 4 copies of each of the specified documents are required;
3. Design and Construction Memorandum.
Documents to be presented:
The original or notarised copy of identification document with the signature of the applicant or legal representative must be produced
Locations for processing the procedure and office hours
Location:
Integrated Services Centre: Avenida da Praia Grande, n.os 762-804, Edifício China Plaza , 2.o andar, Macau;
Northern District Public Services Centre: Rua Nova da Areia Preta, n.o 52, Centro de Serviços da RAEM, Macau;
Central District Public Services Centre: Rotunda de Carlos da Maia, n.os 5 e 7, Complexo da Rotunda de Carlos da Maia, 3.o andar, Macau;
Islands District Public Services Centre: Rua de Coimbra, n.º 225, 3.˚ andar, Centro de Serviços da RAEM das Ilhas, Taipa;
Islands District Public Services Centre – Seac Pai Van Station: Avenida de Vale das Borboletas, Seac Pai Van Community Complex, 6.o andar, Coloane.
Office hours:
Monday to Friday, 9:00 a.m. to 6:00 p.m. (no lunch break, closed on Saturdays, Sundays and public holidays)
Islands District Public Services Centre – Seac Pai Van Station
Monday to Friday, 9:00 a.m. to 1:00 p.m. and 2:30 p.m. to 5:00 p.m. (closed on Saturdays, Sundays and public holidays)
Fees
Not Applicable
Time required for processing
According to the content of alteration application
Remarks/ points to note for application
Important note:
1. The concerned person is required to apply in person or via an authorized person;
2. The above-mentioned documents must be signed by the applicant or legal representative, with the exception of documents issued by government departments or public entities.
Relevant standards or requirements
Not Applicable
Progress enquiry and obtaining result of service
Visit in person to obtain the result